Risk Register

Risk Register#

Document

Risk Register

DRD

No dedicated DRD — risk attributes per ECSS-M-ST-80C (risk management); contributes to SDP §4.5

Container

Management File (MGT)

Project

sar-processor — generic spaceborne SAR data processor

Configuration item

gitlab.eopf.copernicus.eu/ipf/sar-processor

Software criticality

Category C (ECSS-Q-ST-80C Rev.2 / ECSS-E-ST-40C Annex R)

Baselined at

SRR

Status

Draft for SRR — living document

Software engineering contribution to project risk management. Likelihood (L) and severity (S) scored 1–5 per ECSS-M-ST-80C; risk index = L×S. PA-originated and engineering risks are raised as GitLab issues (Risk template) linked to their mitigation merge requests, and reviewed at each milestone. The technical rationale for RSK-05..RSK-11 is developed in the project implementation plan (vault-a-s1-sar-* plan, risks R1–R7).


<1> Register#

ID

Risk

L

S

Idx

Mitigation

Owner gate

Status

RSK-01

Public Sentinel-1 L0 raw decodability (FDBAQ Huffman/BAQ complexity) blocks real-data validation of the L0 decode stage

3

4

12

Extract & study the ESA MPC L0 Decoding Package (DI-MPC-TN-0474) early; bit-exact decode test vs its reference decoded vectors (Inc 1); fall back to reverse-generated ISPs (S2-E2ES reverse-ladder precedent) if reference vectors are insufficient

PDR / Inc 1

Open

RSK-02

Azimuth-focusing complexity (Range-Doppler: SRC, RCMC, TOPSAR deramp/UFR/deburst) exceeds single-developer schedule / correctness reach

4

4

16

Doc-first ATBD (public IPFDPM basis, RD-05); fundamentals-first increments (single-burst point-target validation before TOPSAR); reuse published reference formulations where licence-compatible (SRF)

PDR / Inc 2–4

Open

RSK-03

Single-developer schedule across the full SRR→AR document + code footprint

4

3

12

Tailored Category C DRL (SDP §5.5.2); sensor-agnostic scaffold reused from msi-processor (SRF-RU-01..05); milestone scope control; teaching-hybrid keeps doc + prototype in lockstep

all

Open

RSK-04

SentiWiki/S1 technical-reference ingest gaps leave TBDs unresolved at SRR/PDR

2

3

6

Vault ingest largely complete (ATBD-grade S1 corpus present); TBD/TBC markers tracked per document; SRR gate checks TBD count

SRR/PDR

Open

RSK-05

EOPF Zarr model for complex / burst data — EOZarrStore/EOVariable may not natively represent complex64 or per-burst grouping (plan R1)

3

4

12

Feasibility probe on eopf == 2.8.1 before Inc 2; define a documented complex-split / burst-group convention if native support is absent; record in ICD/SDD

PDR / before Inc 2

Open

RSK-06

Ground-truth scene — the chosen IW datatake may lack corner reflectors / a transponder / a stable-σ0 site, or a matching-IPF SLC+GRD+ADF set, blocking tolerance validation (plan R2)

3

4

12

Select the datatake against a documented cal-site catalogue; source the matched product+ADF set from the Studio VM store; keep the synthetic point-target test as the always-available fallback for focusing correctness

PDR / before Inc 2

Open

RSK-07

L0 Decoding Package completeness — the package may ship only the spec, not decoded reference vectors sufficient for a bit-exact decode test (plan R3)

2

3

6

Inventory the extracted package early; if vectors are absent, derive a reference by round-tripping a real L1→L0 or accept a tolerance-based decode check with documented rationale

Inc 1

Open

RSK-08

DEM choice / licensing / datum — Copernicus DEM vs GETASSE30, ellipsoidal-vs-orthometric geoid handling for GTC (plan R4)

2

3

6

Fix the DEM source + datum convention in the ICD at PDR; unit-test the geoid handling; source DEM from the Studio VM store

PDR / Inc 7

Open

RSK-09

Compute / memory — full IW-datatake focusing may exceed the SDE shell runner / local memory (plan R6)

3

3

9

Per-burst / per-sub-swath chunking (SSS SYS-RES-03); Dask strategy (repo has dask scaffolding); CI Tier-A limited to single-burst / point-target; heavy runs on the Studio VM

CDR / Inc 4

Open

RSK-10

IPF-version gating scope — the matrix of version-gated corrections (EAP phase, noise-vector form, GRD fill) could sprawl (plan R7)

2

3

6

Pin a single supported IPF version for v1 (profile supported_ipf_versions); bound the gating matrix; extend by profile/data later without core changes (SSS SYS-MNT-02)

PDR

Open

RSK-11

product/ subpackage scope — the SAR-specific SAFE/annotation/LUT/orbit I/O layer (a divergence from msi) could grow unbounded or leak framework types into cores

2

2

4

Keep core.py framework-free (arrays + typed params); confine SAFE/annotation parsing to product/; record reuse-vs-new boundary in the SRF (RD-12); design review at CDR

CDR

Open

RSK-12

Bit-identical-reproduction expectation gap — stakeholders may expect pixel-identical reproduction of ESA SLC, which is infeasible without the reference IPF binary

1

3

3

Explicit in SSS §4.3 / SYS-VV-04 and IRD REQ-IF-CAP-04: tolerance-based validation (PSLR/ISLR/IRW, ALE, σ0, burst-overlap phase); bit-exact only for FDBAQ decode

SRR (closed by doc)

Open

Scoring key. L/S: 1 = very low … 5 = very high. Idx = L×S (1–25). Idx ≥ 12 → actively tracked with a milestone gate; Idx 6–11 → monitored; Idx ≤ 5 → accepted/watch.

<2> Closed risks#

None.


Living document — updated at each milestone review (SRevP) and whenever a risk is opened, mitigated or closed via a linked GitLab issue/MR.